FACTORS AND SOLUTIONS TO LIMIT THE SITE CLEARANCE DELAYS IN TRAFFIC CONSTRUCTION PROJECTS

Authors

  • PGS.TS. Hà Duy Khánh

Keywords:

Keywords: Delayed site clearance, construction, transportation projects, project efficiency

Abstract

Abstract: Delayed site clearance poses a significant challenge
in transportation construction investments nationwide. It results in
project operational delays, increased investment costs due to extended
construction timelines, and necessitates adjustments that inflate total
investment, thereby diminishing project efficiency. This study delves
into the underlying causes of sluggish site clearance and proposes
solutions. Through surveys conducted with experts and professionals
from various agencies and organizations, including investors, project
management boards, consultants, and construction contractors, the
study identifies experience in organizing and executing site clearance
as the primary factor. Finally, the study presents three solutions aimed
at improving land clearance progress for transportation construction
investment projects in Can Tho City, based on the analysis and
evaluation findings