Kỹ thuật ước lượng và đánh giá dự án và phương pháp đường găng

Authors

  • Nguyen Thi Thu Hoa

Keywords:

PERT network diagram, PERT chart, CPM, critical task, non-critical task, project completion time, slack, AON, directed acyclic graph (DAG), arrow diagram (AND), networkx, matplotlib, Gantt chart, topological sort.

Abstract

In this paper, we start with a table of project tasks then use Python to create PERT chart and determine critical paths, critical activities, non-critical activities and slacks.

Downloads

Download data is not yet available.

Published

2024-12-05